AI copilot — report summary (demo)
This solar generation facility submitted by SWCA Environmental (synthetic) in Pinal County is a routine undertaking under Section 106 / 36 CFR 800. Auto-matched against the NRHP inventory: 0 listed or potentially-eligible properties fall within or near the project APE. The submitter has provided a pedestrian survey report with photographic documentation.
Draft determination language (Criterion A–D · NHPA §300308): Based on the identified APE, the undertaking will have no adverse effect on historic properties provided the conditions in Section 4 of the submitted report are followed.
Intersecting historic properties
Real data· NRHP matchesNo NRHP properties in the project APE.
Correspondence log (6)
Incoming5/22/2026
Response to RFI
SWCA Environmental (synthetic) → SHPO — J. Begay
Incoming5/22/2026
Submittal: report for review
SWCA Environmental (synthetic) → SHPO — J. Begay
Incoming5/20/2026
Submittal: report for review
SWCA Environmental (synthetic) → SHPO — J. Begay
Outgoing5/13/2026
Request for additional information
SHPO — J. Begay → SWCA Environmental (synthetic)
Outgoing5/4/2026
Request for additional information
SHPO — J. Begay → SWCA Environmental (synthetic)
Outgoing4/23/2026
Concurrence with no adverse effect
SHPO — J. Begay → SWCA Environmental (synthetic)
Documents (2)
Synthetic2 reports + supporting exhibits. Click to preview (stubbed).
Project metadata
StatusInReview
TypeSolar generation facility
Submitter kindconsultant
CountyPinal
ReviewerJ. Begay
Program areaR&C — Telecom/Broadband
Actions