Overdue by 13dPRJ-2026004Synthetic
Solar generation facility — Pinal Co. Phase II
Submitted by AZ Game & Fish · Received 3/13/2026 · Deadline 4/12/2026
AI copilot — report summary (demo)
This solar generation facility submitted by AZ Game & Fish in Pinal County is a routine undertaking under Section 106 / 36 CFR 800. Auto-matched against the NRHP inventory: 0 listed or potentially-eligible properties fall within or near the project APE. The submitter has provided a pedestrian survey report with photographic documentation.
Draft determination language (Criterion A–D · NHPA §300308): Based on the identified APE, the undertaking will have no adverse effect on historic properties provided the conditions in Section 4 of the submitted report are followed.
Intersecting historic properties
Real data· NRHP matchesNo NRHP properties in the project APE.
Correspondence log (11)
Incoming4/21/2026
Submittal: report for review
AZ Game & Fish → SHPO — J. Begay
Incoming4/18/2026
Submittal: report for review
AZ Game & Fish → SHPO — J. Begay
Incoming4/18/2026
Response to RFI
AZ Game & Fish → SHPO — J. Begay
Outgoing4/16/2026
Request for additional information
SHPO — J. Begay → AZ Game & Fish
Outgoing4/12/2026
Concurrence with no adverse effect
SHPO — J. Begay → AZ Game & Fish
Incoming4/9/2026
Submittal: report for review
AZ Game & Fish → SHPO — J. Begay
Outgoing3/31/2026
Request for additional information
SHPO — J. Begay → AZ Game & Fish
Incoming3/26/2026
Response to RFI
AZ Game & Fish → SHPO — J. Begay
Outgoing3/23/2026
Concurrence with no adverse effect
SHPO — J. Begay → AZ Game & Fish
Incoming3/20/2026
Response to RFI
AZ Game & Fish → SHPO — J. Begay
Documents (0)
SyntheticNo reports uploaded yet.